WORKING CONTEXT

The project consiste in the widening and cleaning of a commercial harbor in Georgia.


THE PROBLEM:

Find a very flexible equipment able to work with working depth up to 15m and discharge distance from 200mm and 600m.


OUR SOLUTION:

Dragflow Dredge DRH85/160E22DF: a full optional dredge with 2 dredging unit. The first dredging unit on bord of the dredge to work in the main area of the new harbor and a second unit, mounted on an excavator, to work on the shore.